Planning Phase

Text "8thStreet” to 1-844-238-0330 to receive 8th Street construction information via text message.

Department:
City Engineering
Public Information - George Hayward
Spring 2025
  • Corridor study and design complete 
Spring-Summer 2025
  • Widen 8th Street bridge over Fountain Creek
Fall–Winter 2025
  • Replace water main, Vermijo Avenue to Motor City Drive
Spring-Summer 2026
  • 8th Street roadway work (concrete/paving)
Upload File

About

The project will address infrastructure and mobility needs on 8th Street between Fountain Creek to Motor City Drive. More than 30,000 vehicles use this road daily. It serves as an important link to businesses and neighborhoods southwest of Interstate 25 and U.S. Highway 24.

This PPRTA-funded project was approved by voters in 2012. Initial design work showed that, in addition to road improvements, the corridor needed other significant infrastructure upgrades. Needs included drainage improvements, safer multimodal access, increased capacity on the bridge carrying traffic across Fountain Creek, and a new water main under the roadway.